The estimator wins the job on a Friday. By Monday they are on the next bid, because there is always a next bid.
The project manager gets the contract and a PDF of the estimate summary. The superintendent gets the drawings. Nobody gets the thinking.
The estimate assumed a crew of six with a boom lift on site in week two. It carried a supplier quote that was good for thirty days. It excluded winter heat and hoarding, in a qualification on page four of the proposal. It built the schedule around one area going first so the crew could flow through the rest.
Week three: no lift on order, a crew of nine standing around the wrong area, the quote expired at a higher price, and a heating bill nobody budgeted for. Each of those looks like a small field problem. Added up, they are the margin you bid.
Notes #01 and #02 covered the leak before the bid goes out. This one covers the leak after you win. It often costs more than the first, because nobody is looking for it.
/ SECTION 01The estimate is a plan, and the price is just its total
An estimate looks like a number. Underneath the number sits a plan for how to build the job, and every line of the price depends on it.
- Crew size and mix: how many people, which trades, which ratio of journeypersons to apprentices.
- Productivity rates: hours per unit for each activity, often adjusted for this site's conditions.
- Sequence: what goes first, what can run in parallel, where the crew moves next.
- Equipment: what is on site, when it arrives, owned or rented.
- Quotes: who quoted what, at what price, and how long the price holds.
- Allowances: money carried for items the drawings did not define.
- Exclusions and qualifications: what you told the client you are not doing, or are doing only under stated conditions.
- Contingency: what risk it covers and how much.
If that plan stays in the estimator's head, the field builds a different job from the one you priced. They are not wrong to do it. They never saw the plan.
/ SECTION 02Six places the margin leaks
The leak rarely shows up as one big miss. It shows up as six small ones that each look reasonable on the day.
- Buyout leak. Quotes expire before the PM issues the purchase order, or two subcontract quotes leave a gap between them that nobody owns. You find the gap when the work in it comes due.
- Productivity leak. The budget carries hours, but the field never saw the rates or the crew plan behind them. The super staffs the job the way they staffed the last one.
- Exclusion leak. The PM never read the qualifications. The client asks for excluded work, and the crew does it because nobody knew it was excluded.
- Allowance leak. Allowances get spent as if they were budget, with no reconciliation against what the allowance was for, and no credit or change to the client when the actual cost lands differently.
- Sequence leak. The field starts where it is convenient, not where the estimate assumed. The productivity rates assumed flow, and the crew gets stop-and-start instead.
- Contingency leak. The first problem on the job eats the contingency as general slush, and the risk it was meant to cover shows up later with nothing left to pay for it.
The estimate in the drawer
The handoff is an email with a PDF attached. The estimator moves on, the PM rebuilds a budget from the summary in their own spreadsheet, and the super plans the work from the drawings and their own experience. Three people, three versions of the job, and the only one the client agreed to pay for is sitting in a folder nobody opens until the first cost report looks wrong.
/ SECTION 03The turnover package: seven items
Fix the handoff with a package, built by the estimator before they move on, that hands over the plan along with the price. Seven items, and none of them take long if the estimate was built properly.
- Budget by cost code, loaded from the estimate. Import it. Do not let the PM rebuild it by hand, because rebuilding is where the numbers drift.
- One-page assumptions sheet. Crew size and mix, the key productivity rates, the sequence, and the equipment plan. One page, written for the super.
- Quote register. Every supplier and subcontract quote: who, what scope, amount, the date the price expires, and any gap between quotes that the estimate covered.
- Exclusions and qualifications list. Pulled out of the proposal into a plain list. The PM signs it. The super gets a copy.
- Allowances and contingency. What each one is for, how much, and who can draw on it.
- Top five risks. The risks the estimator saw while pricing, and what they assumed about each.
- Contract terms that cost money. Notice periods, liquidated damages, holdback, insurance and bonding requirements, reporting obligations. The PM needs these in week one, not at the first dispute.
/ SECTION 04The turnover meeting
The package does not replace a conversation. It sets one up.
Hold a ninety-minute meeting before mobilization. In the room: the estimator, the PM, the super, and whoever handles purchasing. Walk the package in order.
The most valuable twenty minutes are the ones where the super challenges the plan. If the super says the sequence will not work, or the crew needs an extra hand, or the lift will not fit through the gate, you just found a cost at zero. Found in week three, the same problem costs real money.
Found in week three, the same problem costs real money.
End the meeting with three things written down: what changed from the estimate, who owns each open item, and the date of the 30-day check.
/ SECTION 05The 30-day check
The estimator stays accountable until the first real cost report. That one rule changes how estimates get built, because the estimator now sees what happened to their plan.
At day thirty, look at three numbers:
- Buyout variance. What you committed to suppliers and subcontractors against what the estimate carried. Most of the buyout should be done by now, and this number tells you early whether the margin survived it.
- Hours against plan on the first activities. Not the whole job. The first few activities, where you can still change the crew, the sequence or the method.
- Open exclusion and allowance items. Any excluded work the client has asked for, and whether a change order went out for it.
Then feed the actuals back to estimating. The productivity rates in your next bid should come from what your crews achieved on this job, not from the rate someone typed in five years ago. The same loop starts to answer test five in note #02: the gap between the margin you bid and the margin you finished at.
/ SECTION 06Five tests for your handoff
Pick a job you mobilized in the last six months and answer these honestly.
- Did the super see the estimate's crew plan and productivity rates before the crew showed up?
- Did the PM sign off a list of exclusions and qualifications, or did they learn them when the client asked for excluded work?
- Was the budget loaded from the estimate, or rebuilt by hand?
- Did any quote expire between award and purchase order?
- Did the estimator see the job's first cost report?
If you answered no to two or more, your margin is leaking between the bid and the build, and you will not see it on the bid-hit-rate report. It lives in the cost reports of jobs you already won.
You can install this yourself. The package is a template, the meeting is ninety minutes, and the check is a calendar entry. Put it on the next job you win and see what the super says in that meeting.