Tuesday morning the owner's rep walks the site and asks the foreman to shift a row of embeds 300 millimetres, since the crew is right there. The foreman does it. It takes an hour.

Wednesday, the answer to an RFI comes back with a support detail no drawing showed. The crew builds it.

Thursday, the crew stands for two hours waiting on another trade to clear the area.

Nobody writes any of it down. It is a good week on site. The client is happy and the work moved.

Six months later, at closeout, the PM sits down to build a claim for all the extra work. They have a phone full of photos, some texts, and a foreman who remembers it differently than the owner's rep does. The client points to the contract: notice was required within a set number of days, in writing, and none was given. The contract agrees with the client.

Most firms have some version of this. The money does not leave in one dispute. It leaves an hour at a time, through crews doing the right thing for the relationship and nobody owning the paperwork.

/ SECTION 01Where the unwritten changes come from

Unbilled scope rarely arrives labelled as a change. It arrives as one of these.

/ SECTION 02Why good crews do not write them up

It would be easy to call this a discipline problem. It is a set of reasonable choices that add up to a bad result.

The foreman does not want to nickel-and-dime a client they will see every day for a year. The change form takes thirty minutes and the crew needs them now. Nobody on the job owns the change log, so everyone assumes someone else has it. The PM plans to batch the changes at month end and month end becomes closeout. And most people in the field have never read the contract's change clause, so they do not know a clock is running.

Fix these with a routine, not a lecture. The routine has to take less time than the excuse.

/ SECTION 03The notice clock

Most construction contracts require written notice of a change, a delay or a claim within a set period after you become aware of it. Miss the window and you may lose the right to be paid for the work, no matter how real the work was.

Read your contract's change and claims clauses before mobilization, and put the notice period in the turnover package (note #06, item seven).

A notice is not a price and it is not a fight. It is a short letter that says: this happened, on this date, we believe it affects our cost or schedule, details to follow. You can send it the same day and price it later.

A notice is not a price, and it is not a fight.
THE COMMON MISFIRE

The closeout claim

The firm does the extra work all through the job and plans to sort out the money at the end. At closeout the PM assembles a claim from memory and photos. The client's team has turned over, nobody remembers the conversations, and the notice window closed months ago. The firm settles for a fraction, or writes it off, and the job that looked fine all year finishes under margin.

/ SECTION 04The weekly change routine

Here is a routine that takes about twenty minutes a week once it is running.

In the field, daily. The foreman logs anything the crew did that was not on the drawings or the plan. One line and a photo, on a phone. No pricing in the field. The foreman's only job is to make sure nothing goes unrecorded.

T&M tickets, signed daily. Where the work is already on time and materials, the client's rep signs the ticket the same day. A ticket signed three weeks later is a negotiation. (Note #05 covers when T&M is the right model in the first place.)

Monday, twenty minutes. The PM, the super and, where possible, the estimator walk through the week's log. Each item gets one of three labels: not a change, potential change, or notice required.

Notice goes out inside the contract window. Short, factual, dated. Send it the day it is identified if you can.

Price within ten working days. Pick your own number, but pick one and hold to it. An unpriced change gets harder to price every week it waits.

One change log, six columns. Every item moves through the same steps:

  1. Identified
  2. Notice sent
  3. Priced
  4. Submitted
  5. Approved
  6. Billed

Anything that sits in one column for more than two weeks gets raised at the next Monday meeting.

/ SECTION 05Two numbers to watch

You do not need a dashboard. You need two numbers, every month.

Both numbers flow straight into your work-in-progress report. Unapproved change work shows up as cost with no matching revenue, and that distorts the margin you think you are earning. Note #08 covers how that hides in the WIP.

/ SECTION 06Writing changes protects the relationship

Owners worry that a steady stream of change notices will sour the client. The opposite is usually true.

A client's project manager has a budget and a boss. A steady flow of small, documented, priced changes lets them manage that budget and explain it upward. A surprise claim at closeout puts them in front of their own boss explaining money they never saw coming. You know which one damages the relationship.

Keep the tone factual, keep the notices short, and keep the pricing fair. The documentation is a shared record that helps both sides.

/ SECTION 07Five questions for your next job meeting

  1. Could your foreman tell you, today, everything the crew did last week that was not on the drawings?
  2. Does everyone on the job know the contract's notice period, in days?
  3. Who owns the change log, by name?
  4. How old is your oldest unpriced change?
  5. What share of your contract value is unapproved change work right now?

If the answers take longer than five minutes to find, you are leaking scope, and the leak only shows up at closeout, when it is too late to fix.

Start the field log on Monday. It costs nothing, and it captures the hour of work you would otherwise give away.

The frameworks are free. The work is the offer.